South Middle School skate-club students told the board that cars collecting students and buses using the parking lot interrupt skating and create safety concerns.
We bring transparency to school decisions nationwide by tracking school board meetings, district documents, and public data. We use AI tools, rigorously evaluated for accuracy, to search for risks.
The policy desk
What’s moving in phones
The debate over phones, screens and the school day.
Central High School’s flood-damaged gym was expected to reopen in about two weeks, after the start of girls basketball practice. Students would practice temporarily at an alternate site while the new floor finished drying and equipment was readied.
Verona Area High School will receive a rooftop solar array under a purchase approved by the board. The roughly $404,000 project combines about $115,000 in community donations with district funding; staff estimate the district’s eventual net cost at about $150,000 if expected credits and rebates arrive.
A committee reported proposed reductions at Oshkosh North’s performing arts center, including flooring, display and lighting changes and removing a closed-caption projector while retaining its infrastructure. The changes offered about $140,000 in potential savings; officials said the total referendum program remained within budget despite the North project exceeding its original estimate. The report did not establish final implementation of every change.
Construction at Franklin Elementary left students without their usual playground this school year. The principal said PTO donations supported alternative recess activities; staff earlier described part of an expanded parking lot serving as a temporary play area. The new parent drop-off loop will remain unavailable during winter construction, with the usual Mason and Fifth Street drop-off continuing.
Janesville reported a $645,000 FEMA award for emergency protective measures after its flood response. Requests covering damaged buildings and contents, as well as future mitigation, remain under review.
Verona approved a project and land lease for a fully accessible, rubberized ballfield near Sugar Creek Elementary. Rotary and Miracle League partners will raise the construction funding; the approval allows fundraising to move forward and does not establish an opening date.
The October 26, 2026 agenda lists boiler replacement at Boyd school, boiler replacement at the high school, a Boyd Early Learning Center fire alarm replacement and a replacement school van, with bids attached.
On October 26 the board formed the Community Facilities Advisory Committee 2.0 (CFAC 2.0). Since September the board has discussed long-range planning for Columbus Middle School and district buildings and grounds.
Staff reported that outdoor picture-and-word communication boards are now installed at every elementary school playground. The boards let students communicate during recess without carrying an electronic communication device.
The board president identified closing the Beloit Memorial High School building as one option under discussion in district reorganization. The interim superintendent said about $5.6 million in reductions must be identified for the next budget cycle; no building closure or specific package of cuts was approved at this meeting.
The board reviewed a proposed 12,500-square-foot fitness addition and boys’ and girls’ locker-room renovation at the high school. The earlier estimate totals $8.2 million; this meeting continued questions and planning without authorizing construction.
Washington Elementary School's referendum renovations remain paused following the spring floods, with other buildings moved forward in the construction schedule. Officials reported that Washington students had been reassigned to Adams and Madison; no Washington reopening timetable was established in this update.
Oak Creek-Franklin is targeting early spring 2027 to open its new aquatic center with competition and community pools. After the new pool opens, the district plans to convert its old pool into a weight room, with completion targeted for summer 2027.
The budget presentation reported that the Beloit Learning Academy program moved from Cunningham into the high school over the summer. Staff also reported relocating transition, early childhood and Even Start programs to Merrill Elementary School.
On Sept. 28 the board voted 4-2, with two abstentions, to sell the property at 5120 Byrd Avenue to the City of Racine Community Development Authority for one dollar. A city presentation describes a new Giese neighborhood housing partnership among the city, the authority, the district and the developer Neumann Companies.
On September 28 staff presented bid information for door access, facility cameras and bus fleet security upgrades paid for by the 2026 referendum. A bid recommendation was due October 26.
Voters approved a $30 million capital referendum in April 2025. At the September 28 meeting the construction team gave an update, and earlier minutes show a groundbreaking was expected in May 2026.
Sheboygan officials warned that Farnsworth Middle School’s renovation could make hot-meal service difficult for a semester. They were considering deliveries from the central kitchen, a rented mobile kitchen or cold meals with a salad bar, and had not chosen a final arrangement.
Parker High School’s planned accessible ramp to the softball fields has been put on hold because April flooding damaged a large retaining wall. Staff said the ramp would eventually be installed, but the district first needs to determine the wall’s repair path through the FEMA process; no installation date was set.
On September 21 the finance committee recommended repairing the high school pool filters after a valve failure, replacing an Intermediate School chiller unit, and planning to replace worn middle school bleachers. A pool evaluation will resume.
The board approved up to $885,000 from the capital expenditure fund (Fund 46) for a secure entrance at Oostburg Middle School. The plan moves the main office so visitors enter at a controlled point. The architect expects bidding this fall or winter and construction to start in summer 2027.
The district planned to seek bids for the River Heights bus loop project that week, targeting construction during summer break in 2027. The package also includes sidewalk work around the entrance and rear of the building.