ourschoolboard.org Find my school

District news

Environmental assessment findings reported for Wood Middle School construction project

Alameda Unified School District · Jun 9, 2026

High-risk

What happened

At the June 9, 2026 meeting, staff reported that soil testing at Wood Middle School's Measure B construction site found levels mostly consistent with natural background, but a localized area near a former transformer required remediation; the Preliminary Environmental Assessment was submitted to DTSC and entered a 30-day public review period.

Why it matters to families

This confirms a documented environmental issue (contamination near a former transformer) at a school construction site that required remediation, relevant to school community safety.

The evidence

Minutes: 'a localized area near a former transformer was remediated, and additional testing in the soccer field and garden areas produced results below regulatory screening levels.'

The source

Approved board meeting minutes

Get alerts like this for Alameda Unified School District

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.

Get personalized alerts